Desperation for Energy in a hurry ….

NANT POWER Ownership in Public Scrutiny

By Mahmud Tim Kargbo

A US$417 million power station is rising at Kissy, but Sierra Leoneans still cannot readily establish who ultimately owns it, what their Government has promised or who pays if the investment fails. Financial close was announced in November 2024, backed by US$292 million in United States Development Finance Corporation (DFC) financing and a 22year Power Purchase Agreement (PPA). The country needs electricity, but necessity cannot excuse opacity in a contract capable of shaping public finances for decades. Who owns Nant, who negotiated its terms and how much financial risk has been transferred to the Sierra Leonean people?

DFC identifies CECA SL Generation Limited as the borrower, not the Government of Sierra Leone, and approved up to US$292 million in senior debt. It separately approved political risk insurance of up to US$120 million for CEC Africa (Sierra Leone) Limited or an eligible affiliate. The ECOWAS Bank for Investment and Development provided US$40 million, while the sponsors contributed US$85 million in equity, according to Anergi’s financial close announcement. These instruments are distinct: insurance is not a sovereign guarantee of the DFC loan. Nevertheless, government undertakings, PPA payments, foreign exchange provisions, liquidity support and termination obligations could expose public finances to substantial liabilities. https://www.dfc.gov/sites/default/files/media/documents/BDR%2824%2921.pdf; https://www.anergigroup.com/anergi-announces-financial-close-of-the-nant-project-in-sierra-leone/

The sovereign guarantee question demands an unequivocal answer. A 2016 World Bank appraisal proposed an IDA guarantee of up to US$40 million to Sierra Leone in support of CECA SL, alongside proposed IFC and MIGA instruments. That proposal does not establish that a guarantee was executed or applies to the present DFC loan. Section 118 of the 1991 Constitution regulates government borrowing and agreements involving public funds, while the Public Debt Management Act 2011 provides the statutory framework for public debt and guarantees. Has Government executed any guarantee, indemnity or other financial undertaking for Nant, and, if so, where is the parliamentary approval? If the private borrower defaults, who bears the contractual loss? https://www.parliament.gov.sl/constitution-of-sierra-leone.html; https://www.sierra-leone.org/Laws/2011-02.pdf; https://ppp.worldbank.org/sites/default/files/2022-03/103305-PAD-P153805-IDA-R2016-0174-1-Box396252B-OUO-9.pdf

Ownership remains unresolved. DFC’s environmental assessment identifies CEC Africa (Sierra Leone) Limited as CECA SL’s parent, with Milele Energy holding 50.1 per cent and TCQ Power 49.9 per cent, although another passage describes equal interests. Anergi subsequently identified Harith InfraCo and the Pan African Infrastructure Development Fund 2 as its owners. The 2016 World Bank appraisal traces TCQ’s historical ownership through VICI Holdings SAL, identifying Muhammad Nasser and family members as VICI’s owners. These historical records neither establish current beneficial ownership nor prove that Muhammad Nasser is Karim Nasser. Government and the project company must disclose every shareholder, controlling interest and ultimate beneficial owner. https://www3.dfc.gov/Environment/EIA/ceca/ESIA.pdf; https://www.anergigroup.com/anergi-announces-financial-close-of-the-nant-project-in-sierra-leone/; https://ppp.worldbank.org/sites/default/files/2022-03/103305-PAD-P153805-IDA-R2016-0174-1-Box396252B-OUO-9.pdf

Nant’s history began long before the 2024 financial close. DFC records that Government reviewed three proposals for approximately 120MW in 2010, followed by Cabinet approval of the foundational framework in July 2011. The original 128MW PPA was signed on 14 May 2014, laid before Parliament on 23 May and ratified on 29 May, according to the Hansard. Ibrahim R. Bundu laid the agreement on behalf of the Energy Minister, while a contemporary account identifies Attorney General and Justice Minister, Frank Kargbo, as presenting it for ratification. Henry Macauley subsequently laid project documents in 2017, while the January 2017 Deed of Termination introduces a conflicting 29 May 2015 ratification date that requires parliamentary clarification. https://www3.dfc.gov/Environment/EIA/ceca/ESIA.pdf; https://www.parliament.gov.sl/uploads/handsards/23rd%20May%2C%202014.pdf; https://www.into-sa.com/enews/first-independent-power-producer-ipp-approved/; https://www.parliament.gov.sl/uploads/loans/Deed%20Of%20Termination%20Of%20Project%20PRA%20314.pdf

In December 2021, Energy Minister, Alhaji Kanja Sesay, presented the amended 148.5MW PPA, which Parliament ratified on 21 December. Timothy Kabba also appears in the Votes and Proceedings in connection with the Government motion, although the records require clarification of their respective roles. Kanja Sesay presented another amendment on 19 October 2023, describing a 22 year concession, a 26 year land lease and eventual transfer of the plant to Government. His presentation quoted capacity charges of 7.238 US cents per kWh for LPG and 7.038 cents for LNG, with fuel separately priced. At the Bank of Sierra Leone reference rate of NLe22.88 to US$1 on 18 November 2026, the LPG charge translates to approximately NLe1.66 per kWh, excluding fuel and other applicable costs. https://www.parliament.gov.sl/uploads/votes/5TH%20PARL.%20V%26P.%20-%20TUE.%2C%2021ST%20DEC%2C2021%20FINAL.pdf; https://www.parliament.gov.sl/uploads/press_release/pdf/PARLIAMENT%20RATIFIES%20ENERGY%20AGREEMENT-%2021st%20DECEMBER%2C%202021.pdf; https://www.parliament.gov.sl/uploads/handsards/19TH%20OCTOBER%20%2C%202023.pdf; https://bsl.gov.sl/Indicative%20Exchange%20Rates%2018-11-2026.pdf

The procurement question remains unanswered. The Public Private Partnership Act 2014, particularly section 66, addresses transitional arrangements for earlier agreements and projects that had not reached financial close. Nant reached financial close in 2024, making the precise legal basis for its contractual evolution a matter requiring public explanation. The 2016 World Bank appraisal records the review of three generation proposals and competitive selection of certain engineering, construction, operations and fuel contracts. That does not establish that the original concession itself satisfied every applicable procurement requirement. Where are the feasibility studies, value for money assessments, Cabinet decisions, procurement evaluations, legal opinions and approvals? Parliament’s ratification cannot substitute for evidence that the entire process complied with the law. https://www.parliament.gov.sl/uploads/acts/The%20Public%20Private%20Partnership%20Act%2C%202014.pdf; https://ppp.worldbank.org/sites/default/files/2022-03/103305-PAD-P153805-IDA-R2016-0174-1-Box396252B-OUO-9.pdf

The Government’s own parliamentary commitments provide another test of accountability. Kanja Sesay described gas turbines, fuel storage, a jetty pipeline, a new substation and transmission reinforcement. He told Parliament that construction was expected to begin in the fourth quarter of 2023, with commercial operation targeted within 36 months. These were ministerial statements, not proof of delivery. Government and the developer should publish the original construction schedule, revised completion dates, commissioning milestones, fuel supply agreements and performance guarantees. More fundamentally, the Hansard identifies SHAKA Sierra Leone Limited.  as the project company, whereas DFC identifies CECA SL Generation Limited as the borrower. Which company holds the concession, which carries the contractual obligations and how are the two entities legally connected? https://www.parliament.gov.sl/uploads/handsards/19TH%20OCTOBER%20%2C%202023.pdf; https://www.dfc.gov/sites/default/files/media/documents/BDR%2824%2921.pdf

The fiscal risks cannot be considered separately from EDSA’s financial condition. The Auditor General’s 2023 report estimated technical and commercial losses at NLe411.8 million, while the 2024 audit identified 22 non operational thermal plants with 45.98MW and six non operational hydro plants with 6.7MW. The International Monetary Fund has also identified electricity sector arrears and weak revenue collection as fiscal risks. These findings do not establish wrongdoing by Nant, but they make the affordability of its contractual obligations an urgent public concern. The SLPP’s 2023 manifesto promised completion of the 128MW project and improvements in EDSA’s financial and technical performance. How will Government prevent the PPA, fuel price exposure and possible termination liabilities from becoming another burden on taxpayers and electricity consumers? https://website.auditservice.gov.sl/wp-content/uploads/2024/12/2023-AGs-REPORT-Final-2-12-24.pdf; https://website.auditservice.gov.sl/wp-content/uploads/2025/12/Auditor-Generals-Annual-Report-2024.pdf; https://www.elibrary.imf.org/view/journals/002/2026/168/article-A001-en.xml; https://statehouse.gov.sl/wp-content/uploads/2023/08/The-Full-New-Direction-Manifesto-Consolidating-Gains-And-Accelerating-Transformation-Thursday-23-May-2023.pdf

Environmental accountability is equally necessary. DFC classified Nant as Category A, identifying projected annual greenhouse gas emissions of approximately 430,450 tonnes of carbon dioxide equivalent and assessing fuel transportation, storage, pipeline infrastructure, water consumption and community impacts under relevant environmental standards. Its assessment also warned that inadequate transmission and distribution infrastructure could prevent electricity from reaching customers and generating revenue. Government should publish updated environmental monitoring, emissions records, safety audits and compliance findings. The generating capacity also requires reconciliation: parliamentary presentations refer to 103.5MW and 148.5MW, while DFC’s 2024 financing resolution identifies approximately 105MW. Such differences should be resolved through the executed PPA and technical schedules, not left to public speculation. https://www3.dfc.gov/Environment/EIA/ceca/ESIA.pdf; https://www.dfc.gov/sites/default/files/media/documents/BDR%2824%2921.pdf

Sierra Leone should welcome investment that expands electricity supply, but it must never confuse investment with accountability. Who owns Nant today; what did Parliament approve; was the concession lawfully procured; what financial obligations did Government accept; and who pays if the project defaults or fails to deliver? These are legitimate questions, not hostility towards private enterprise. Until the ownership records, contracts, guarantees, procurement decisions and financial exposures are disclosed, citizens cannot determine whether Nant is a national asset or an expensive obligation passed to future generations. A power station should illuminate a country’s homes, not leave its people in the dark about who owns it and what they have been made to pay.